Tuesday, August 26, 2008

Pouring the Footings

First, I really need to mention what a thrill it is to see the outline of the house in a real 3D world. I've been looking at it strictly on paper so long, I didn't think this day would ever come!

Usually when a house is built, there's plenty of access around the perimeter for the concrete truck to go, and they get the concrete where it needs to be via the shoot on the truck. Not in this case. There is only one spot to pull up a truck of any kind, so it needs to be pumped in. The pump truck is always an "extra" with any concrete contractor, so you need to budget for it accordingly. There are 2 kinds of pump trucks, ones with a boom which delivers the concrete from over head ($1,200/day), and one that pumps the concrete along the ground with a long hose ($600/day).

Before the day arrived for the pour, I called my concrete contractor (his name is "Mo" btw) to make sure he was going to use the cheaper one. He wasn't. Nice try Mo, but not any more. Obviously, it's easier to use a boom truck than to have to muscle around a big heavy hose, but I can't blame him for trying.

On the day of the pour, the pump truck pulled in first, set its outriggers for stability, and assembled the hose sections. Altogether, about 120 feet of hose was needed to reach the far corner. Then the first of 5 concrete trucks pulled in and started to empty its load in the pump trucks hopper and away we went.

Pouring the footings is pretty straight forward, just pour up to the level of the "nails" (as described earlier) and smooth it out. Once the concrete starts to set up a bit, they take a stick and carve a "key way" into the top of it. The key way creates a "tongue and groove" joint between the foundation walls and footing, making it hard for water to penetrate. Finally, more rebar is added, this time vertically every 2 feet, so the walls and footings will be joined together permanently.
video

Monday, August 18, 2008

Setting the Forms for the Footings

The first step in installing a foundation is to mark out and install the footings. The footings are a continuous band of concrete, about a foot thick which runs under the foundation walls. The purpose the footings is to distribute the weight of the walls to a larger surface area to minimize any settling. Usually footings are 2 feet wide, but my contractor likes to make his 3 feet wide.

Using lasers as a guide, the contractor drives stakes into the ground, representing each outside corner of the foundation. This, of course includes all the jogs and angles of the walls. Then, for more accuracy, he drives a nail into the top of each stake so each corner is exactly marked.

Once the foundation walls are marked, more stakes are driven, this time creating a line 1 foot to the outside of the foundation walls and one foot to the inside. This represents where the footings go. The dirt is dug out to a 1 foot depth and forms are laid. Accuracy isn't too critical at this stage. If the forms are off by a couple of inches either way it won't make too big of a difference. The height if the forms is important, but not critical. So long as the top of the forms are about 1 inch above the final footing height, all is fine.

Once the forms (BTW, the "forms" in this case are merely lengths of 2 x 12's) are all set, 3 pieces of reinforcing bars (rebars) are placed inside to reinforce the footings. The rebars are set on top of bricks to keep them in the air to ensure that they'll be embedded in the footing later.

In New York, it's that law that footings must be at least 3 feet below the final grade. If they weren't, when the ground freezes in winter, it would expand, lifting the house. It doesn't' take many cycles of freeze/thaw to do real damage to the structure. The depth of the footing, of course, varies with the climate of the area. I mention this because we're having a side entry garage, which is at basement level. So here, the footings needed to be another 2 feet deep. When I came to the job site after all the forms were set, I noticed this was not the case, so the contractor had to make them deeper. This is why constant checking up is necessary when building a house.

Once the forms are in and the rebar is set, a final level line must be established so the tops of all the footings are at the exact same level. Here again they use a laser level. Here's how it works: First they set up the level on a tripod where it won't be disturbed. Then they take an electronic receiving device and attach it with a clamp to a 4 foot stick. After some calibration, all the worker has to do is place the stick against the inside of the form and move it up and down as he listens. As the laser gets close to the correct mark on the receiving device, it starts to beep. When the stick is at the exact height, there is a continuous tone. At this point the worker takes a nail and drives it onto the side of the form, just under the 4 foot stick. Repeat the above operation about 200 times and you've got a perfectly level line throughout.

Besides the wall footings, there are also a number of "piers" that need to be set. The piers act like footings in that they distribute weight, but instead of a wall sitting on them, there will be lally columns. The lally columns will later support the steel that will be used as the main beams of the house. The plans called for the piers to be 3 foot square x 18 inches deep, but I decided to make them 4 foot square at the last minute.

The final step is to oil the forms. Oil is necessary to make it easier to strip the forms away from the dried concrete later on. The oil is applied with an industrial bug sprayer. Now we're ready to pour the footings!

Tuesday, August 5, 2008

Digging the Hole

Last week the surveyor staked out the house location. The way they do it is to drive stakes into the ground 20 feet from the sides and in the same plane as the front and back of the house. They do it this way because if they were to mark the exact corners, obviously the stakes would be destroyed as soon as the excavator started digging.

The excavator got started last Wednesday. It took him about a day and a half to pull out the stumps and put them in the dumpster. It took two 30 yard dumpsters to handle all the stumps. The actual digging started on Friday. The excavator figured it would take 2 days to dig but I went there yesterday and could see that it will probably take more like 4.

The hole is only half dug but there are gigantic piles of dirt everywhere! Remember earlier that I mentioned we had sectioned off a “clearing line” of 30% of the property? Well, now the trees that were 20 feet outside the clearing line are buried about 15 feet deep!

The foundation contractor is scheduled to begin on Friday. There aint no way he’ll be able to get a concrete truck around the perimeter, so that means I’ll probably have to provide for a pump truck to pump the concrete to the back part of the house.

Of the 2 framing contractors I mentioned in the previous post, I got a number from one of them and he was pretty pricy. The other one I met yesterday at the job site to discuss things. He should be getting back to me soon with a price.

Thursday, July 17, 2008

Permit Approved, Trees Cut!!

The permit was supposed to take 3 weeks to process but it wound up taking more like 5. Well, at least they didn't discover any missing documentation that would have prolonged things even more.

Yesterday, I met the tree clearing contractor at the property to go over the job. The surveyor had already staked out the clearing boundaries a few weeks ago. When I built the house we're in now, 20 years ago, I thought I was saving money by doing the clearing myself. I had to rent a chipper for 3 days at $450 per day and the job took me and a helper over a week to do. Oh yeah, my back was practically broken by the time I was done.

This time I hired a contractor to do the work. He showed up with a crew of 4 and lots of equipment to do the job, including a massive chipper aptly named: "The Intimidator". They blew the whole job out in one day for the bargain price of $1,690. Money WELL spent.

I called my surveyor to get him scheduled to come in to stake out the house location. He said he'd get to it by the beginning of next week. My excavator and foundation contractors are eager to get started.

The only potential problem right now is the framer. I called him yesterday to let him know what's what and he said he was about to start a really big job and won't be able to get on ours until 2 1/2 months from now. I located a couple of other framers and am printing out sets of plans for them both. Who knows, with the housing industry in a slow down, maybe I'll get better pricing.

Wednesday, June 4, 2008

Finally.... We've submitted our building permit application

I can't believe the hassle of just submitting an application for a building permit. I finally got the the drawings reviewed by an engineer who stamped them with his seal of approval. Then, I went down to the Southampton Town Hall thinking I had all my documents in order. WRONG!!

Turns out I needed some kind of approval from the highway department. OK, another hoop to jump through, whatever... The local government here really doesn't waste any opportunity to squeeze money out of people. The fee for this approval was $100. A C-note so someone in the highway dept can look something up in a book and then stamp a piece of paper. And for this privilege I had to wait another 2 weeks to boot.

Anyway, the highway approval finally came in last week and I immediately ran down to the building dept. to apply. I don't think I'll ever forget spreading all of my documents out on the table and studying the face of the woman who was helping me. Just waiting for the slight grimace and shake of the head as she prepared to tell me that they needed something else. To my amazement, that shoe never dropped and I could have kissed her when she told me the building dept. fee was $3650. It meant everything was in order. Now we have to wait about 3 weeks for the permit (which is 2 weeks from now). We can't so much as cut down a tree until we get it.

Meanwhile, we've been working on our existing house to get it ready for sale. It could take a year or more to sell and it looks best this time of year. We'll probably wind up having to rent a house for a short time before the new house is ready.

Thursday, March 13, 2008

Trees Planted

As a condition of the sale of the property, we had to install a row of trees along the back border as a privacy screen. To guarantee compliance, we had to put up $10,000 in escrow, to be held by our lawyer. The trees were installed a few days ago and they look great. It's so nice to be actually be DOING something!

We got back bids from most of subs I sent them to. Prices were a little higher than I had hoped for but I guess that's to be expected.

I wasn't happy with where the architect had originally placed the house on paper, so I moved it back about 20 feet. I was concerned that there would be too little privacy from the front. I sent the new site plan to the surveyor yesterday. He has to stake off the exact house location so the excavator knows where to dig.

Friday, February 1, 2008

I got the plans last week from the architect. I had to make several last minute tweaks to them and I’m printing them right now. I’m glad I told my architect to lay the drawings out on 24” x 36” paper because I have a printer that can handle that size. I got a list of potential subcontractors from a builder friend of mine and should be able to mail everything out in a few days.